Valley Transit District, Derby, CT Cost: $7.8M | Project Area: 16,000 sf / 1.7 acres

Programming and environmental assessment and organizing site vehicular movement. Combination of a “fuel—wash—park” entry sequence generated the basis of the site design.

Task:

  • Master plan, building expansion and upgrade for existing administrative, maintenance and garage facility

Challenge:

  • 7 acres
  • Organizing site vehicular movement
  • Future fleet of 20 busses, some larger vehicles than currently handled.
  • Turning radius or large wheelbase vehicles –30-passenger 34’ busses
  • Full-wash-park entry

Solution:

  • Phased construction keeping existing facility in operation.
  • Create a new egress path allowing for a temporary closing of the main entrance.
  • Design for the turning radius of large wheelbase vehicles combined with a “fuel—wash—park” entry sequence generated the basis of the site design.